Imagine a race where the finish line is perpetually shifting, always seeming just out of reach. This metaphor aptly illustrates the current legal debate surrounding Section 29A of the Arbitration and Conciliation Act, 1996 (A&C Act, 1996) and the possibility of extending an arbitral tribunal’s mandate after an award has been delivered. Section 29A, introduced through an amendment in 2015, was designed to enhance the efficiency of arbitral proceedings by imposing strict timelines for issuing arbitral awards. However, the interpretation of this provision has led to a series of conflicting decisions and legal uncertainties, especially regarding whether the tribunal’s mandate can be extended after the award has been issued.

The Purpose and Evolution of Section 29A

The 2015 amendment to the A&C Act marked a significant shift in the regulation of arbitration in India. Section 29A was introduced to impose specific deadlines on the arbitral process, with the primary objective of ensuring timely resolution of disputes. According to Section 29A, arbitral tribunals are required to deliver their awards within twelve months from the date they commence proceedings. This timeline aims to prevent delays and enhance the efficiency of arbitration.

However, the amendment initially created confusion about whether this twelve-month period applied to both domestic and international arbitration. To address this uncertainty, a High-Level Committee chaired by Justice B.N. Srikrishna was formed. The committee recommended that the twelve-month timeline should commence only after the completion of pleadings and should not apply to international commercial arbitrations. Based on these recommendations, Section 29A was further amended in 2019, clarifying that the twelve-month period applies only to domestic arbitration, with a provision for a six-month extension by mutual consent of the parties.

Under Section 29A(3), if the tribunal fails to deliver the award within the specified period, its mandate is automatically terminated unless the court grants an extension. This extension can be sought before or after the deadline, but only on the application of any party and for sufficient cause.

Judicial Interpretations and Conflicting Decisions

The interpretation of Section 29A has been the subject of considerable judicial scrutiny, resulting in conflicting decisions by various High Courts. These conflicting judgments revolve around whether a court can extend the tribunal’s mandate after an award has been delivered, and what the true scope of Section 29A is in this regard.

Madras High Court’s Interpretation

In Suryadev Alloys and Power Pvt. Ltd. v. Shri. Govindaraja Textiles Pvt. Ltd., 2020 SCC OnLine Mad 7858, the Madras High Court provided a critical interpretation of Section 29A. The court highlighted the shift from the Arbitration Act of 1940 to the A&C Act of 1996, noting that the earlier Act allowed courts significant flexibility in extending the time for making an award. In contrast, the 1996 Act, through Section 29A, aimed to streamline the arbitration process by imposing strict deadlines.

The Madras High Court ruled that once an arbitral award is pronounced, the tribunal’s mandate terminates automatically. Any application for extending the mandate must be made before the expiration of the tribunal’s mandate. The court emphasized that extending the time limit post-award is not permissible, as it would undermine the strict timelines set by Section 29A.

Delhi High Court’s Divergent Views

In Powergrid Corporation of India Ltd. v. SPML Infra Ltd., 2023 SCC OnLine Del 8324, the Delhi High Court reaffirmed the strict interpretation of Section 29A. The court ruled that an application for extending the tribunal’s mandate under Section 29A is not tenable once the award has been delivered. The judgment reasoned that Section 29A does not expressly provide for extensions after the award is issued, and thus, such a provision is not implied. The court maintained that if the legislature intended to retain provisions similar to those in the 1940 Act, it would have explicitly included them in the 1996 Act.

Conversely, in National Skill Development Corporation v. Best First Step Education Pvt. Ltd., 2024 LiveLaw (Del) 265, the Delhi High Court took a slightly different approach. The court allowed an application for extension under Section 29A if it was filed before the award was made and the award was delivered while the application was pending. This judgment indicated that while the tribunal’s mandate typically ends with the award, an application for extension filed before the award remains valid if the award is rendered during the pendency of the application.

Kerala High Court’s Approach

The Kerala High Court has offered a contrasting perspective in RKEC Projects Limited v. The Cochin Port Trust, 2024 SCC OnLine Ker 4192. The court ruled that an application under Section 29A is maintainable even after the award is delivered, provided there is a sufficient cause for extension. The court argued that the termination of the tribunal’s mandate under Section 32 is not absolute but can be subject to the court’s power to extend the mandate under Section 29A.

According to the Kerala High Court, while Section 32(1) stipulates that arbitral proceedings terminate with the final award, this termination is not absolute. The court maintained that Sections 29A(3) and (4) provide the court with the authority to extend the tribunal’s mandate even after the award is issued, as long as there is sufficient cause.

Implications and Considerations

The conflicting judicial interpretations of Section 29A reveal several important implications and considerations:

1. Practical Implications

The strict timelines imposed by Section 29A aim to prevent delays and enhance the efficiency of arbitration. However, the rigid interpretation, as seen in the judgments from the Madras and Delhi High Courts, may not always accommodate the practical realities of complex disputes where additional time may be required. The flexibility offered by the Kerala High Court’s ruling provides a potential remedy for cases where extensions might be justified due to genuine reasons.

2. Judicial Flexibility vs. Legislative Intent

The tension between judicial flexibility and legislative intent is a central theme in these decisions. The A&C Act, 1996, through Section 29A, sought to introduce a more structured and efficient arbitration process. However, the conflicting judgments highlight the challenges in balancing this structure with the need for flexibility in exceptional circumstances.

3. Supreme Court’s Role

The Supreme Court’s intervention is crucial in resolving these conflicting interpretations. A definitive ruling from the Supreme Court could provide much-needed clarity on whether Section 29A allows for post-award extensions and under what circumstances. Such a ruling would help standardize the application of Section 29A and address the current legal uncertainties.

4. Future of Arbitration Practice

The ongoing debate and conflicting decisions reflect broader issues within the arbitration framework in India. The resolution of these conflicts will shape the future of arbitration practice, influencing how arbitrators and parties approach deadlines and extensions in arbitration proceedings.

Conclusion

The debate over extending tribunal mandates post-award under Section 29A of the A&C Act highlights the complex interplay between statutory deadlines and practical needs. While Section 29A was designed to ensure timely resolution of disputes, the conflicting judicial interpretations underscore the need for a balanced approach that accommodates both efficiency and flexibility. The Supreme Court’s forthcoming decisions will be pivotal in clarifying the scope of Section 29A and providing a cohesive framework for addressing extension requests in arbitration. Until then, the legal community will continue to grapple with the shifting finish line of arbitration deadlines.

Leave a Reply

Your email address will not be published. Required fields are marked *

This field is required.

This field is required.

Disclaimer

The following disclaimer governs the use of this website (“Website”) and the services provided by the Law offices of Kr. Vivek Tanwar Advocate & Associates in accordance with the laws of India. By accessing or using this Website, you acknowledge and agree to the terms and conditions stated in this disclaimer.

The information provided on this Website is for general informational purposes only and should not be considered as legal advice or relied upon as such. The content of this Website is not intended to create, and receipt of it does not constitute, an attorney-client relationship between you and the Law Firm. Any reliance on the information provided on this Website is done at your own risk.

The Law Firm makes no representations or warranties of any kind, express or implied, regarding the accuracy, completeness, reliability, or suitability of the information contained on this Website.

The Law Firm disclaims all liability for any errors or omissions in the content of this Website or for any actions taken in reliance on the information provided herein. The information contained in this website, should not be construed as an act of solicitation of work or advertisement in any manner.